Scheduled power interruption in parts of SORSOGON
The National Grid Corporation of the Philippines (NGCP) serves notice
of the scheduled shutdown of the following transmission facilities:
Date: 21 January 2014
Time: 8:00AM – 5:00PM
Affected
Distribution Utility: * SORSOGON ELECTRIC COOPERATIVE 2 ( SORECO 2)
Reason: Commissioning and energization of primary
metering system at Balogo load-end substation.
Normal operations will
immediately resume after work completion. NGCP customers and the general public
are advised to take necessary preparations and precautions for this scheduled
interruption.